If the buyer has contracted for e.g., 10MW today, but the required need down the road is 8MW? Can buyer resell the MWh unused as unbundled RECs?

The SPP and CC must affirm the capacity under their contract. Please be aware of Clause 5.7 when designing the plant. REC is not a product under NEDA. Buyer cannot resell the unused energy as unbundled RECs.