If the ESA has already been signed with a scheduled start date, how will delays in the GEP be managed if there is no corresponding delay from the Green Consumer (GC)? Would TNB be open to provide temporary supply to GC in case the GEP is delayed? i. If T

i. Under the Clause 6.10, TNB, as a supplier of last resort, will provide full and/or balance of electricity supply as required by the GC based on the T&C in the Electricity Supply Agreement, independent of the readiness of the GEP.

ii. Any compensation due to delay from the RED may be covered under the Bilateral Agreement between RED and GC.

iii. The maximum allowable delay period may be covered under the Bilateral Agreement.