Under the Clause 6.18 - Bill issued from SB to RED, item (c) mentioned “relevant NEDA charges, and other services (if any)”. Please elaborate what constitutes relevant NEDA charges and what other services will be charged by SB?
NEDA charges referring to market/administrative fee (which includes other costs as per direction by the Government (e.g., tax, levy, etc)).